Frame material was delivered a week ago but nothing happening. Received an email from building coordinator advise about frame work completed by 19 December 2014. Seems planning to 2nd Payment before Christmas Holiday..
Porter Davis Prestige. A Sandringham 45 in Mount Waverley, Melbourne. Knockdown rebuild!
Monday, December 8, 2014
Thursday, November 27, 2014
Sunday, November 9, 2014
Work Started – Cut and Fill
The work started and land is cut-fill as per the drawings. Retaining wall and pier work performed-
The land looks quite high from the back. Landscaping will be expensive :-)
Thursday, November 6, 2014
Site Cost Increased
Received an email from Building coordinator that site cost will increase by $12k. What the hell. The reason given were:
With no option left and stuck, we proceed with this. Felt really cheated and can’t believe PD did so much underestimate…
Monday, October 27, 2014
Monash Council – Nature strip backfill
Received letter from Monash Council to backfill the nature strip in 2 days else fine will be issues. Found quite wired as we still need to build the house and this all will damage. Called them but was very unhelpful. Finally ordered topsoil from Garden Gear and backfill the nature strip. Send an email to Council with no reply….
Thursday, October 16, 2014
Second Soil Test
Informed Porter Davis that land is ready for handover to them. PD ordered second soil test. Seems all going good!
Friday, October 3, 2014
Crossover Damaged
The crossover has been damaged by the demolition company due to electric pit not installed properly. Send an email to Zinfra for the same. Received reply with blame shifted to demolition company. Council people from Asset protection department believe this was demolition company fault.
Lucas from Melbourne City Demolition took ownership and work with Zinfra to fix this.
Lucas from Melbourne City Demolition took ownership and work with Zinfra to fix this.