Met SS and told that handover will be in next 3-4 weeks; exciting time.
Spend whole weekend finalising the furniture
Blinds finalised...
Porter Davis Prestige. A Sandringham 45 in Mount Waverley, Melbourne. Knockdown rebuild!
Sunday, May 3, 2015
Wednesday, April 29, 2015
Thursday, April 16, 2015
Wednesday, March 11, 2015
Thursday, January 22, 2015
Sunday, December 14, 2014
Monday, December 8, 2014
Frame material delivered.. Nothing happening
Frame material was delivered a week ago but nothing happening. Received an email from building coordinator advise about frame work completed by 19 December 2014. Seems planning to 2nd Payment before Christmas Holiday..