Thursday, November 27, 2014

Sunday, November 9, 2014

Work Started – Cut and Fill

The work started and land is cut-fill as per the drawings. Retaining wall and pier work performed-

FullSizeRender (1) FullSizeRender (2) FullSizeRender (4) FullSizeRender (5)

The land looks quite high from the back. Landscaping will be expensive :-)

 

f5ca789ffcd52c34c2436be4c78ccbc1

Thursday, November 6, 2014

Site Cost Increased

Received an email from Building coordinator that site cost will increase by $12k. What the hell. The reason given were:

0 

 

With no option left and stuck, we proceed with this. Felt really cheated and can’t believe PD did so much underestimate…