We went to Narre-warren office and met the tender person who was very helpful. The process went really smooth and we met our building contractor for first time.
The biggest shock was the site cost that increased from $40 to $47k. We were told that this is due to soil test report and estimated on higher side for any future risk.
We asked for changes in the plan to stay under the budget which were quicky updated. Provided $10K deposit and ready for colour selection and demolition process.
Learning: You will need full half day for tender process – so make sure you have made arrangement for kids to be picked up.